Jump menu

United States

United States

Country Selector

Secondary Navigation | back to top

Main content |  back to top

Exploration and Discovery
The discovery well was drilled in 1987 by Transocean’s drillship, Discoverer Seven Seas. One delineation well was drilled. The target reserves are in the Upper Miocene "I" sand, at a depth of approximately 15,500 feet. The average net thickness is approximately 100 feet.
Development
Mensa initially consisted of three wells connected via individual 6-inch infield flowlines to a subsea manifold five miles away, which is then tied back to a shallow water platform at West Delta 143 via a 63-mile 12-inch flowline. This 68-mile tieback formerly held the record for the longest in the world. The previous tieback record was 30 miles for the Troll Oseberg Gas Injection project in the Norwegian sector of the North Sea.
 
Shell then developed and began production from Mensa's fourth well in 2003.  Transocean's Marianas drilled Mensa 4. The Mensa 4 well produces through a 4 mile long 8-inch infield flowline to the subsea manifold. 

The Mensa A-5 was drilled in 2007 (drilled by the Noble Jim Thompson) and the A-6 in 2010 (drilled by the Transocean Nautilus).  The A-5 well shares an infield flowline with the A-3 well, and A-6 shares an infield flowline with the A-1 well.  These wells draw from the same sands as the first three wells.

Timeline for Installation of the major components
Timeline for Installation of the major components
January 1997 Electrical distribution structure 
March 1997 Subsea manifold/template
February/March 1997 All hydraulic and electrical umbilicals and the three infield 6-inch flowlines
May 1997    12-inch flowline from the manifold to West Delta 143
July 1997   First tree
Fall 1998 Tree installation continued as the final well was drilled and completed. Jumpers were installed following each tree installation.
1Q 2003 Mensa 4 tree and 4 mi flowline to central manifold installed, and well began production
July 2007 Mensa 5 begins production through new expansion sled to the A-3 infield flowline.
December 2010 Mensa 6 begins production through new expansion sled to the A-1 infield flowline.
Production

Production of Mensa's initial three-well system began in July 1997. Production began from the Mensa 4 in March 2003, Mensa 5 in July 2007 and Mensa 6 in December 2010. The additional development wells were needed to replace wells that either mechanically failed or watered out. Currently, the A-1, A-3 and A-4 wells are either partially or fully abandoned.  The field has produced 844 BCF to through May 2011.